SQL · Power BI public dashboard · ALX Africa integrated capstone, Project 4
Maji Ndogo Water Funds
A public accountability dashboard tracking how water infrastructure money was spent, and where it overran.
+5.3%over budget, program-wide
- MySQL
- Power BI
- DAX
- Shape map

01Business problem
Public infrastructure spending is only trustworthy if people can see it. Citizens and auditors needed to see budget vs. actual cost for each water-source improvement, which vendors were paid, and whether work was on schedule, by province and by rural vs. urban location.
02Data
- Source
- Maji Ndogo survey and infrastructure dataset (ALX integrated project)
- Size
- 25,398 completed improvement projects, plus water-source and well-test records
- Limitations
- Maji Ndogo is a fictional country built for training, so the figures are realistic but not real-world. Costs are modelled, not audited invoices.
03Tools & methods
- MySQL for exploration
- Power BI data model with DAX measures
- Shape map for geographic view
- Five-page report design
04Cleaning & preparation
- 1.Explored cost structures, improvement types and completion timelines in SQL before modelling.
- 2.Modelled infrastructure_cost and project_progress tables in Power BI.
- 3.Wrote DAX measures for budget variance and cumulative cost vs. budget over time.
05Key findings
- GHS 7.76MThe program ran 5.3% over budget: GHS 154.5M spent vs. GHS 146.7M budgeted.
- +26.5%“Diagnose local infrastructure” overran by 26.5% (GHS 3.23M vs. 2.55M). Most other improvement types were 3–6% over.
- GHS 44.8MSokoto province had both the highest spend and the largest overrun: GHS 4.7M over budget across 5,603 projects.
- 54%Installing RO filters and drilling wells account for GHS 83.1M of total spend.
- 12,467Of 17,383 tested wells, 12,467 were contaminated, and 64% of sources are still below basic access.
06Dashboard & visuals



07Recommendations
- Audit the “Diagnose local infrastructure” line first. Its 26.5% overrun is about five times the program average.
- Prioritise a Sokoto cost review: it carries the largest absolute overrun.
- Tie remaining funds to contaminated wells, since over two-thirds of tested wells failed.
08What I'd do next
- Add vendor-level variance (quoted vs. charged) to flag individual contractors.
- Publish to the web with row-level views per province for local officials.